Agile Roadmap
I see responses implying that the development roadmap is decided for a year at a time. As WA grows, that is going to become a huge problem.
I suggest changing to a model where you revise the roadmap each quarter. The next 3 months should be pretty firm, but beyond that you should be able to consider user reaction and new ideas much faster.
This might seem like a lot more work, but it really isn't. Each cycle, you do detailed project planning for the next quarter, refine the scope of work for the next 2 quarters, and plan strategy for the newly added quarter.
Awesome point and we’re actually in the process of making huge organizational changes so it’s really relevant. But not really a feature suggestion :) Closing for now.